An investment process
Within preparation of the investment basic information concerning the real estate where the investment is due to be carried out is inevitable , i.e. legal status, location, access to a public road and laying of pipes, sewers, power lines in the area as well as building conditions and the designation of the real estate in the local master plan.
In case there is no local master plan concerning particular location, the Investor shall apply for determining the building development conditions issued in a form of a decision.
Attention: in accordance with the Act of 27 March 2003 about spatial planning and development (Law Gazette of 2003 No 80 item 717 with further amendments), issuing a decision concerning building development conditions is possible only if all the following conditions are fulfilled:
• at least one of the neighbouring plots, accessible from the same public road is developed in a way which allows determining requirements concerning the new building site within the scope of continuing its function, parameters, features and indicators/rates of shaping the building site as well as the area development, including dimensions and the architectural form of the building objects, the building line, and the intensity of the area usage;
• the area has an access to a public road;
• existing or designed laying of pipes/sewers/power lines is sufficient for the building plan – this condition is believed to be fulfilled if making pipes/sewers/power lines in the area is guaranteed by the agreement between a proper organisational unit and the investor;
• the area does not require obtaining an approval for a change of the designation of the arable and forest land for non-agricultural and non-forestry purposes or is included in the approval obtained while making local plans which are no longer legally valid due to Art. 67 in the Act of 7 July 1994 about spatial development;
• the decision is in conformity with separate regulations.
Obtaining inevitable permits and a decision as well as making an investment
Having finished an initial phase of the investment process and possessing the right to use the real estate, the Investor shall obtain all the essential permits or make a notification of all the planned works. The course of action in this phase is dependent on the kind and range of the planned building undertaking.
Construction works can be started only on the basis of a final decision about permission for the building works (or a decision about permission for a demolition). Attached you can find kinds of works that need no permission.
Kind of the construction undertaking can decide about the necessity of obtaining a decision about environmental conditions of the undertaking. It occurs when the investment planned can have a significant impact on the natural environment. Obtaining an environmental decision for such undertakings is required before starting the process of obtaining a building permit.
An investor is obliged to inform about the date of starting the construction works. The building process must be carried out and supervised by authorised persons.
Finishing works – technical acceptance
After carrying out the construction works there is still the last phase left which consists in technical acceptance of the object by proper institutions and possibly obtaining a right of usage. A right of usage form and the notification about finishing the construction works are submitted to the County Inspector of Building Works Supervision (PINB). It is a government administration organ.
In Dąbrowa Górnicza the Inspector is based in the building of the City Hall, 21 Graniczna St. 21, tel. + 48 32 295 69 24; 295 69 25; room number 021B (ground floor).
In case there is no local master plan concerning particular location, the Investor shall apply for determining the building development conditions issued in a form of a decision.
Attention: in accordance with the Act of 27 March 2003 about spatial planning and development (Law Gazette of 2003 No 80 item 717 with further amendments), issuing a decision concerning building development conditions is possible only if all the following conditions are fulfilled:
• at least one of the neighbouring plots, accessible from the same public road is developed in a way which allows determining requirements concerning the new building site within the scope of continuing its function, parameters, features and indicators/rates of shaping the building site as well as the area development, including dimensions and the architectural form of the building objects, the building line, and the intensity of the area usage;
• the area has an access to a public road;
• existing or designed laying of pipes/sewers/power lines is sufficient for the building plan – this condition is believed to be fulfilled if making pipes/sewers/power lines in the area is guaranteed by the agreement between a proper organisational unit and the investor;
• the area does not require obtaining an approval for a change of the designation of the arable and forest land for non-agricultural and non-forestry purposes or is included in the approval obtained while making local plans which are no longer legally valid due to Art. 67 in the Act of 7 July 1994 about spatial development;
• the decision is in conformity with separate regulations.
Obtaining inevitable permits and a decision as well as making an investment
Having finished an initial phase of the investment process and possessing the right to use the real estate, the Investor shall obtain all the essential permits or make a notification of all the planned works. The course of action in this phase is dependent on the kind and range of the planned building undertaking.
Construction works can be started only on the basis of a final decision about permission for the building works (or a decision about permission for a demolition). Attached you can find kinds of works that need no permission.
Kind of the construction undertaking can decide about the necessity of obtaining a decision about environmental conditions of the undertaking. It occurs when the investment planned can have a significant impact on the natural environment. Obtaining an environmental decision for such undertakings is required before starting the process of obtaining a building permit.
An investor is obliged to inform about the date of starting the construction works. The building process must be carried out and supervised by authorised persons.
Finishing works – technical acceptance
After carrying out the construction works there is still the last phase left which consists in technical acceptance of the object by proper institutions and possibly obtaining a right of usage. A right of usage form and the notification about finishing the construction works are submitted to the County Inspector of Building Works Supervision (PINB). It is a government administration organ.
In Dąbrowa Górnicza the Inspector is based in the building of the City Hall, 21 Graniczna St. 21, tel. + 48 32 295 69 24; 295 69 25; room number 021B (ground floor).