Guide for Investors
Registration of construction works
Before starting construction works an administrative decision permitting starting and carrying out construction works or building works shall be obtained.

A permit for construction works can concern the whole building plan or in case of a bigger project only some indicated part of it.
 
The decision expires after 3 years from the date of its coming into force or if the construction works are interrupted for a period of more than 3 years.

In case of some works, obtaining a building permit is not required, only making the notification .

NOTIFICATION ABOUT BUILDING OBJECTS OR CARRYING OUT CONSTRUCTION WORKS


The department responsible: Urban Planning and Architecture Department 

Required documents:
•    construction works notification /form no. 10/

•    a statement of the right to have the power of attorney to have the real estate at one’s disposal

•    a drawing presenting the range of works

•    permits, opinions, agreements required by separate laws or regulations

•    In case of building architectural details  in public places, additionally a project of the development of the plot or the area made by a designer with required building qualifications shall also be presented

•    in case of construction works:

- tank system for liquid gas with an isolated tank  of the capacity up to 7 m3, designated for  feeding gas systems in single-family housing

- connections: power grid, waterworks, sewage system, gas systems, heating and  telecommunications

Moreover, a plot (or area) development project along with a technical description of the systems and fittings made by a designer with proper building qualifications shall be attached.

Fees/charges:
there are no charges  for the notification of building works

Deadlines:
the building works can be started unless within 30 days from the date of submitting the notification the proper body makes a refusal, and not later than  after 2 years from the deadline of starting works indicated in the notification.

Legal basis: :  The Act dated 07 July 1994 – Building Law (harmonized text: Law Gazette from 2006 r. No. 156 , item. 1118 with further amendments).

Documents to be downloaded


special suggestion
Location: vacant land property located in Dąbrowa Górnicza-Kazdębie, on road №790, leading to the Łosień district.
Location: undeveloped land property located in the transitional zone of the city, in the area of the former KWK Paryż mine. The plot fronts directly onto ul. Siemiońskiej, within Będzin’s boundary.
Location: a property located in the central area of Dąbrowa Górnicza, in the Gołonóg district, in Aleja Zagłębia Dąbrowskiego.
see all
If you have a question
Ewa Fudali-Bondel
+48 32 295 96 97
efudali@idabrowa.pl
Paweł Zygmunt
+ 48 32 295 96 93
pzygmunt@idabrowa.pl
sitemap | RSS | | contact
© Copyright by Town Hall in Dąbrowa Górnicza A.D 2009. All rights reserved.
The project is co-financed by the European Union from the European Regional Development Fund within a framework of the Regional Operational Programme for the Silesian Voivodship for the years 2007 – 2013.